December 2018 – Advance in French Guiana Power Plant

The construction of the Power Generation Plant in French Guiana moves forward; Berkes team continues working to guarantee the execution of the project according to the quality and deadline standards that identify us.

In Cacao, 80 km south from Cayenne city, civil works such as the equipment foundations, offices, turbine room, etc. are being carried out. Meanwhile, in Serbia, the manufacturing of the water-tube boiler which will deliver 23 TPH of steam, 68bar (a) @ 485ºC continues.

At the beginning of 2019, Berkes project team will arrive on site to start the logistics operations, assemblies and subsequent commissioning works.

That passion for what we do is strengthened when our work contributes in the use of renewable sources for generation of electricity in Latin America and the rest of the world.